Hurricane Rehabilitation Project

 

Phase I - June 1997 - May 1998:  

Client: The Ministry of Communications, Works and Public Utilities of the Government of St. Christopher and Nevis.

Consultant: A De B Consultants Limited, Jamaica

Scope of Works

The project involved the construction of Sea Defence structures at four separate sites on the island of St. Kitts.

 Works included:

v  Construction of approximately 3,200 feet of rock armoured Sea Defences.

v  Roadway realignment.

v  Drainage construction.

v  Construction and paving of approximately 400 sq. yards Parking area.

v  Construction of 8’ wide Sidewalk and Blockwall.

v  Placing of Filter Fabric for Slope Protection.

Phase II - June 1997 - May 1998:

June 1997 - May 1998: Hurricane Rehabilitation Project – Phase II  St. Kitts

Client: The Ministry of Communications, Works and Public Utilities of the Government of St. Christopher and Nevis.

Consultant: A De B Consultants Limited, Jamaica

Scope of Works

The project involved the Construction of Sea Defence structures along three separate Coastal roads and the Rehabilitation of 315 m of damaged sections of roadways.

Specifics of the project included but were not limited to the following:

Ø  Construction of approximately 645 m of Armoured Sea Defence Works.

Ø  Construction of Culvert Crossings, Side Drains and Sidewalks.

Ø  Construction of Pedestrian steps, Drainage facilities and a Boat ramp. 

Hurricane Lenny Rehabilitation

April 2005 - February 2006: Hurricane Rehabilitation Project - St. Kitts

Client: Ministry of Communication & Works of the Government of St. Christopher & Nevis

Scope of Works

The project involved the construction of Sea Defence Structures along two (2) coastal sites on the island of St. Kitts.

Both sites consisted of Rock Armoured Sea Defence Works and Road Shoulder Rehabilitation.

New Guinea:

            - 420 metres in length.

            - Comprising of Corefill and rock of various sizes from 20kg to 3.0 tonnes resulting in 77,100 tonnes of Armouring installed.

Old Road Bay:

            - 230 metres in length.

            - Comprising of Corefill and rock of various sizes from 20kg to 3.0 tonnes resulting in 16,200 tonnes of Armouring installed.

 

Sea Defence Works

February 1999 - October 2002: Sea Defence Works – Gouyave, Grenada

Client: Ministry of Communications and Works, Grenada

Consultant: Smith Warner / CEP Ltd., Grenada

 The job involved Construction of 373 m of road and 330 m of rock revetment consisting of rocks from 10 kg – 7.5 tonnes.

This project was funded by USAID as part of the Western Main Road Upgrade.

Trinidad Contractors Limited mobilized on site and started extraction of rocks from two quarry sites using D8 Bulldozers to extract, sort and stock-pile rocks, which were loaded onto trucks by excavators and transported to the site that was located one (1) mile from the quarries.

Whilst work was being carried out at the quarries, a concrete crew worked at our Trinidad base pre-casting concrete elements to be used on the new seawall. The pre-cast elements were shipped to Grenada on our Barge S222, which was towed by our tug ‘Comanche Arrow’ and installed into position; the intermediate and upper portion of the wall were cast insitu.

1.   Excavation   

2.   Rock Armour                                 

3.   Fill 

4.   Rebars

5.   Concrete

6.   Kerb and Slipper Drains

7.   Swale Drains

8.   Pavement

9.   Base Material

10.  Asphalt

11.  750 diameter Concrete Culverts

2,418 m³

40,000 tonnes

5,500 m³

54 tonnes

490 m³

458 m

117 m

530 m²

3,036 m²

3,036 m²

90 m

Trinidad Contractors Limited also excavated, hauled, installed and compacted backfill material behind the new sea wall, after which a crush stone base was installed and compacted.

 

Civil Jobs

Some samples of Civil Projects Done

Marine Jobs

Samples of  Marine and Sea Defence Projects Completed

Asphalting Jobs

Samples of some Asphalt  Projects Completed

 
 

Maintained by FenShu Services