We milled out a depth of 2 inches from the central 80 feet width and full width at each end of a 8,000 feet runway, cleaned surface, tack and lay 9,000 m.t. of Hot Mix Asphaltic Concrete.
All work was done at night.
Trinidad Contractors Limited transported and stored its bitumen requirement with in-house marine equipment and tankage.
Our 90 tonnes per hour mobile batch type Asphalt Plant and materials laboratory were established on the Airport compound.
SAN RAFAEL BRIDGE
October 2006 – May 2009: Bridge B1/1, San Rafael Road
Client: Ministry of Works and Transport
Consultant: Lee Young and Partners/Roughton International