The job was awarded to Trinidad Contractors Limited on 5th May, 1988 with an official handover of the Site on 12th July, 1988 and the commencement of a 12 month Contract period on 18th July, 1988.

The project entailed the Construction of 11 No. Buildings which accommodates the following:

v  Industrial Arts (2 buildings).

v  Classrooms.

v  General Science.

v  Social Studies.

v  Administrative Home Economics.

v  Hall.

v  Agriculture.

v  Toilet Facilities.

v  Security Booth and Bus Shelter.

v  Snackette.

Whilst the Civil works encompassed the construction of:

   
 
 

Cedros Composite School

July 1988 – June 1989: Cedros Composite School - Trinidad

Client: Ministry of Education and Culture

Architect: Reynald Associates Limited