Yara Retaining Wall

June 2005 - August 2005: Yara House Retaining Wall - Tobago

Client: Yara Trinidad Limited

Scope: This project required the removal of the existing wall and replacing it with a 10 feet High x 1 foot Thick Reinforced Concreting Retaining Wall.

 

Terrance B. Lettsome International Airport

May 2001 - Nov. 2002: Terrance B. Lettsome International Airport

   Phase 1A Developments, Package 3
  Airside Infrastructure
   Beef Island, British Virgin Islands
   

Client: Government of the British Virgin Islands, Development Planning Unit

Consultant: Netherlands Airport Consultants B.V., The Netherlands

Introduction

The Contract for the Airside Infrastructure was awarded to Trinidad Contractors Limited as part of the Airport Expansion Project.

The work had to be carried out in Phases, so as to have the Airport operations functional at all times.

Project Details

The work comprised of five (5) phases which included items of work as follows:

  1. Demolition of existing Terminal Buildings, Structures and Utilities (above and underground), Road and Airfield Pavements and Site Clearance.

  2. Earthworks and Drainage works, including environmental protection measures.

  3. Asphalt concrete overlay on existing apron.

  4. Construction of Asphalt Concrete pavement extension to aircraft parking apron, including service roads.

  5. Fuel Resistant Seal Coat and Pavement Markings.

  6. Apron Floodlighting – concrete foundations, light poles, cabling, light fixtures and dual obstruction lights.

Remarks

Ø  Safety on the project was a very important aspect and regular communications were necessary between the Airport Control Tower and the Work Site.

Ø  An Asphalt Plant of Batch Type was installed on site as part of the Contract requirements for the production of Asphaltic Concrete.

Ø  As part of the Contract, the company provided a Mobile Materials Laboratory for the Quality Control / Quality Assurance.

Ø  Trinidad Contractors Limited utilized its Marine Support (Barge and Tug) to mobilize plant and equipment and materials to the Site. A berthing facility adjacent to the work site was upgraded to enhance this service.

Ø  Bulk Bitumen (60/70 penetration grade) was stored at the Berthing area using 2 No. 40,000 gallon tanks equipped with heating and discharging facilities.

Civil Jobs

Some samples of Civil Projects Done

Marine Jobs

Samples of  Marine and Sea Defence Projects Completed

Asphalting Jobs

Samples of some Asphalt  Projects Completed

 
 

 

Maintained by FenShu Services